A company is developing a linear programming model for its aggregate production plan. If
W_(t)
- workforce size for period t ,
H_(t)
number of workers hired for period
t
, and
F_(t)
= number of workers fired for period
t
, then the company's workforce constraint for period 2 is
W_(2)=H_(2)-F_(2)
W_(2)=W_(1) H_(2)-F_(2)
W_(2)-W_(1) F_(2)-H_(2)
W_(2)=H_(2)-F_(2)-W_(1)