A permit is obtained on Friday, May 1. The materials are to be delivered on May 8. The materials are needed when labor begins on May 11. It is estimated that 15 days of labor are REQUIRED. The crew will work every day, including weekends and holidays. The project is scheduled to be completed on June 8. How many float days are available for the labor for this project? 

please explain it



We have an Answer from Expert

View Expert Answer

Expert Answer


Ans. 13 float days available for labor - because i