(Solved): Barbara Gordon, the project manager for Web Ventures, compiled a table showing time estimate for ea ...
Barbara Gordon, the project manager for Web Ventures, compiled a table showing time estimate for each of the company's manufacturing activities of a project. The list of activities, immediate predecessors, and estimated times appear in the following table: a) Therefore, the critical activities for the manufacturing project are
b) The total length for the manufacturing project = days. c) Slack time for each of the activities are as follows: