Chapter 6 Exercise Name: _________________ • Using the following information, develop an AON project network. Complete the forward and backward pass, compute the activity slack, and identify the critical path. Answer the following questions: • What is the critical path? • How many weeks to complete? • What is the slack for activity C? For activity F? Activity Predecessor Time (Weeks) A None 4 B A 5 C A 4 D B 3 E C, D 6 F D 2 G E, F 5