Question#1: Calculate the expected time and construct the network diagram Calculate the ES, EF, LS \& LF of each activity. Wh
Show transcribed data Question#1: Calculate the expected time and construct the network diagram Calculate the ES, EF, LS \& LF of each activity. What is the duration of the proj completion. Determine the critical path. What's the probability of completing project within 47 weeks.


We have an Answer from Expert

View Expert Answer

Expert Answer


Solution: Activity to tmtpExpectedTimete=to+4?tm+tp6 Variance ?2=(tp-to6)2 A 1 2 3 2 0.11 B 2 3.5 8 4 1 C 6 9 18 10 4 D 4 5.5 10 6 1 E 1 4.5 5 4 0.44