Home / Expert Answers / Operations Management / given-the-following-project-all-times-are-in-days-a-draw-the-network-and-find-the-critical-pat-pa998

(Solved): Given the following project (all times are in days): (a) Draw the network and find the critical pat ...



Given the following project (all times are in days): (a) Draw the network and find the critical path, time, and cost for an all-normal level of project activity. (b) Calculate the crash cost-per-day (all activities may be partially crashed). (c) Find the optimal way of getting an 18-day delivery time. What is the project cost? (d) Find the optimal way of getting a 16 -day delivery time. What is the project cost? (e) Calculate the shortest delivery time for the project. What is the cost?



We have an Answer from Expert

View Expert Answer

Expert Answer


We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe