QUESTION 2 (8 MARKS) Car gear box maintenance operation and each station capacity at DinGomok Sdn. Bhd. workshop are shown in Figure 1. The lubrication operation occurs separately from, but simultaneously with, the greasing operation. All operations are done manually. Only one operator is assigned to each station. Figure 1: Gear box maintenance operat?ons and each station capacity a) The workshop operates 8 hours per day, 22 days per month. Determine which station is the bottleneck and subsequently calculate the monthly capacity of the above maintenance operations process. (4 marks) b) Due to budget constraint, the maintenance operation is not allowed to work overtime. Instead, they are allowed to increase the station capacity. If the company predicts an average of 2000 units to be serviced each month, suggest how this demand can be served without any problem. Show the calculation to justify your suggestion. (4 marks)