Product A requires 9 minutes of milling, 7 minutes for inspection, and 6 minutes of drilling per unit; product B requires 10 minutes of milling, 5 minutes for inspection, and 8 minutes of drilling per unit; product C requires 7 minutes of milling, 3 minutes for inspection, and 15 minutes of drilling. The department has 20 hours available during the next period for milling, 15 hours for inspection, and 24 hours for drilling. Product A contributes $5.8 per unit to profit, product B contributes $7.1 per unit, and product C contributes $6.2 per unit. How do you express the objective function mathematically? NOTE: Let A,B, and C denote respectively the number of A, B, and C to be produced.

a. Max A + B + C

b. Max 5.8 A Max 7.1 B Max 6.2 C

c. Min 5.8 A + 7.1 B + 6.2 C

d. Min A + B + C

e. Max 5.8 A + 7.1 B + 6.2 C



We have an Answer from Expert

View Expert Answer

Expert Answer


Question – a: Constraints are for: 1. Milling hours 2. Inspection hours 3. Drilling hours 4. Non-negative of A 5. Non-negative o