Q 5. Minimum water elevation on upstream side of a diversion weir's Spillway is 400m. a) The minimum flowrate is 94m3/s, thalweg elevation on upstream side of the spillway is 394m, and effective crest length is 50m. Please find the height of spillway. (Cmin=1.88) b) The maximum flow rate is 430.86m3/s, so please calculate the maximum spillway head, by neglecting approach velocity on upstream side. (Cmax=2.18) c) By obtaining maximum spillway head and maximum flowrate as Project Spillway Head and Project Flowrate, compute the water depth at the toe of structure, average velocity value and Froude Number on this zone, (Assume effective crest length and stilling basin channel width are the same.) d) By calculating the downstream side depth ( y2) of hydraulic jump, determine the stilling basin type and its dimensions. Q=C∗B∗h1.5;y2=2y1∗[1+8∗NFr12−1]
a) To find the height of the spillway, we can use the minimum flow rate and the given coefficient:Minimum flow rate (Q) = 94 m^3/sCoefficient ( ) = 1.88We can use the following equation to calculate the height of the spillway (h): where B is the ef...