Riverbed planned to produce 6300 units but only produced 5600 for the current year. The company had a beginning inventory of 380 units with a variable manufacturing cost of
$10per unit. Budgeted fixed
MOHfor the year was
$69300with actual costs incurred of
$64300. What will Riverbed report as the fixed
MOHprice variance for the current year?
$5000U.
$2700F.
$2700U.
◻
$5000F.