Home / Expert Answers / Mechanical Engineering / subject-production-planning-and-controllan-electronics-manufacturer-makes-remote-control-devices-fo-pa539

(Solved): #subject-Production planning and controllAn electronics manufacturer makes remote control devices fo ...



#subject-Production planning and controll



An electronics manufacturer makes remote control devices for interactive-cable-TV systems. The following assembly tasks must be performed on each device.


(a).Draw the precedence diagram for this problem.

(b).What cycle time will allow the production of 200 units over a ten-hour day?

(c).What is the theoretical number of workstations needed?

(d).Balance this assembly line using the heuristic most following tasks.

(e).Determine the balancing efficiency


\begin{tabular}{|c|c|c|}
\hline Task & Predecessor(s) & Time \( (\mathrm{min}) \) \\
\hline A & - & 0.50 \\
\hline B & A & 0.
\begin{tabular}{|c|c|c|} \hline Task & Predecessor(s) & Time \\ \hline A & - & 0.50 \\ \hline B & A & 0.70 \\ \hline C & B & 0.40 \\ \hline D & C & 0.30 \\ \hline E & - & 0.30 \\ \hline F & - & 0.20 \\ \hline G & E, F & 0.35 \\ \hline H & D & 0.40 \\ \hline I & G, H & 0.60 \\ \hline J & I & 0.30 \\ \hline \end{tabular}


We have an Answer from Expert

View Expert Answer

Expert Answer



The table represents a project with different tasks and their respective information. Here's a breakdown of each column:

Task: This column lists the tasks involved in the project, identified by letters (A, B, C, etc.). Predecessor(s): This column indicates the task(s) that need to be completed before a particular task can start. For example, task B requires task A to be completed first.
We have an Answer from Expert

Buy This Answer $5

Place Order