(Solved): The fifth unit of a 25 -unit job took \( 14.5 \) hours to complete. If a 90 percent learning curve ...



The fifth unit of a 25 -unit job took \( 14.5 \) hours to complete. If a 90 percent learning curve is appropriate: \( a \). How long should it take to complete the last unit? b. How long should it take to complete the 10 th unit? c. Estimate the average time per unit for the 25 units.