The following Activity on Arrow (AOA) network diagram shows the information about 4 different
activities in a semester projec

The following Activity on Arrow (AOA) network diagram shows the information about 4 different activities in a semester project. Earliest start time D,7 a. Determine the earliest start time for activity F. Latest finish time b. If the latest time activities E and F are to be finished is 13, determine the latest finish time for activity C. Activity C D E E,3 c. What is the slack for each activity? WE F,5 F Slack


We have an Answer from Expert

View Expert Answer

Expert Answer


Answer: Earliest start time (ES) of C = 10 Earliest start time of D = 8 Earliest finish time (EF) = ES + Duration Duration of C = 7 Duration of D = 5 EF of C = 10 + 7 = 17