(Solved):
Two 10kW,50Hz,230V, 1-phase power generators operating in parallel are supplying a 1-phase l ...
Two 10kW,50Hz,230V, 1-phase power generators operating in parallel are supplying a 1-phase load. The load power and the power factor are measured to be 16.34kW and 0.84 lagging, respectively. Line impedance between the generator and the load is 0.28+j0.02?. The generators are capable of regulating the terminal voltage at the rated value using high-end AVRs. You are expected to calculate the generator supply currents.