Home / Expert Answers / Operations Management / which-statement-best-defines-the-purpose-of-having-a-liquidated-damages-contract-question-2-optio-pa949

(Solved): Which statement best defines the purpose of having a liquidated damages contract? Question 2 optio ...



Which statement best defines the purpose of having a liquidated damages contract? Question 2 options: a) A contract that liquidates the assets of the contractor if they run late on the project. b) A contract that assures the client that they will be compensated for losses if the project runs late. c) A contract that requires the client to compensate the contractor if that make changes that cause the contractor to be late. d) A contract that places a punitive penalty for the contractor if the contractor ends up running late on the project.



We have an Answer from Expert

View Expert Answer

Expert Answer


We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe