You are the project manager doing an assessment of the Earned Value Analysis. Your latest report gives you the following details. Cost Performance Index (CPI) = 1.2, Schedule Performance Index (SPI) = 0.8, Planned Value (PV) = $500,000, Schedule Variance (SV) = -$220,000. What is the Cost Variance (CV) of the project? $80,000 $60,000 $66,667 $33,333