Home / Expert Answers / Operations Management / you-are-the-project-manager-doing-an-assessment-of-the-earned-value-analysis-your-latest-report-giv-pa225

(Solved): You are the project manager doing an assessment of the Earned Value Analysis. Your latest report giv ...



You are the project manager doing an assessment of the Earned Value Analysis. Your latest report gives you the following details. Cost Performance Index (CPI) = 1.2, Schedule Performance Index (SPI) = 0.8, Planned Value (PV) = $500,000, Schedule Variance (SV) = -$220,000. What is the Cost Variance (CV) of the project? $80,000 $60,000 $66,667 $33,333



We have an Answer from Expert

View Expert Answer

Expert Answer


We have an Answer from Expert

Buy This Answer $5

Place Order

We Provide Services Across The Globe